High-speed rail link between three airports to start this year

Photo courtesy of Bangkok Post

The high-speed rail project connecting Don Mueang, Suvarnabhumi, and U-Tapao airports is set to kick off later this year following a revised agreement between the state and project developers.

Anan Phonimdang, Deputy Governor of the State Railway of Thailand (SRT), confirmed that the SRT’s board has acknowledged the agreement. The Eastern Economic Corridor (EEC) Policy Committee and the Cabinet will review the matter to ensure the state benefits from the project. The Notice to Proceed (NTP) is anticipated to be issued by the end of the year.

Advertisements

Asia Era One, a consortium led by CP Group, secured the 224.5 billion baht contract to construct the rail system in 2018. However, the project, a key infrastructure development within the EEC, faced delays due to various issues, including the impact of the pandemic.

Negotiations between the SRT, the Office of the EEC, and the consortium have led to modifications in the contract to ensure project completion.

Related news

“The solution is clear and based on principles. The company is required to submit an additional bank guarantee as an assurance it will be completed.”

The contract revision covers four main areas: the payment of the joint venture right, government investment in the project, an additional bank guarantee, and investment promotion privileges.

Under the revised terms, Asia Era One will pay the joint venture right in full, plus interest, amounting to 11.7 billion baht, in seven instalments. The state’s investment in the project will commence 18 months after the NTP is issued, rather than immediately after the trains start operating. The company is required to submit an additional bank guarantee of 111.9 billion baht within 270 days of the contract revision.

Advertisements

Original budget

Originally, the government committed to investing approximately 111.9 billion baht under a public-private partnership scheme. This includes 3.57 billion baht for land appropriation, with the remaining 108.33 billion baht to be paid starting in the sixth year or after the commencement of train operations.

Asia Era One has requested that the government provide payments for ongoing construction work. For the NTP to proceed, the company must first receive an investment promotion certificate from the Board of Investment. However, the state has agreed to remove this requirement after the review process concluded yesterday, reported Bangkok Post.

Anan stated that if the NTP is issued as planned, the construction is expected to be completed by 2029.

Aviation NewsBangkok NewsThailand NewsTransport News

Puntid Tantivangphaisal

Originally from Hong Kong, Puntid moved to Bangkok in 2020 to pursue further studies in translation. She holds a Bachelor's degree in Comparative Literature from the University of Hong Kong. Puntid spent 8 years living in Manchester, UK. Before joining The Thaiger, Puntid has been a freelance translator for 2 years. In her free time, she enjoys swimming and listening to music, as well as writing short fiction and poetry.

Related Articles

Check Also
Close