Pattanakarn footpath project completion six weeks away
The Pattaya Mail is reporting that the first phase of construction of footpaths along Naklua’s Pattanakarn Road should be completed in about six weeks.
Engineering chief Thongchai Kamlangthai reported that the project started on September 28 and was now partially finished with a large section of footpath for pedestrians and joggers already to use.
Reinforced concrete pavements are being laid alongside the roadway through Moo 10 and Moo 13 villages. The sidewalks will be 1.8 metres wide spanning some 3.5 kilometres.
Supattra Joint Venture, the contractors for the project, say they will complete the first phase by the end of April, Thongchai said.
The second phase will be started from the front of Tarapattana School to Tungkom-Tanman Road. Neither phase is affecting traffic through the areas.
SOURCE: Pattaya Mail
Pattaya NewsLeave a Reply
You must be logged in to post a comment.